top of page

Sonora Courthouse

Client:

Turner Construction


MVE was responsible for providing land surveying and construction staking services for the new Sonora Courthouse project. This two-story justice facility spans 61,537 square feet and had a state-funded budget of $71,326,000. The courthouse features five courtrooms, eight public service counters, eleven holding cells, administrative offices for a lawyer facilitator and mediator for family court, accommodations for five judges and support staff, an official county law library and self-help center, as well as two jury deliberation rooms.

Construction began in 2019 and was completed in 2021, with the facility opening to the public on November 15th of that year.

Location:

Sonora, CA

PARTNER WITH MVE

Get your project done right with an experienced full-service team.

bottom of page